General Contractor: Tilcon Connecticut Inc.
Start Date: 5/10/2021
Completion Date: November 2021
Subcontractors or Key Contractors: Black and Boucher: Milling, CT Traffic Control, Olmstead Contracting: Concrete Flatwork, Safety Marking: Pavement Markings

Materials Used on Project and Quantities:>

  • 61,000Tons HMA
  • 480,000 SY milling
  • 45,000 SF concrete walks

Project Summary:

Strong coordination and communication was required throughout the project in order to efficiently complete the list.Organizing and batching the streets together by location was an important aspect to allow for the crews to be productive without jumping between locations.The completion of sidewalk ramps was also part of the contract on various streets throughout the list. Activities throughout included day and night work to successfully complete the project.This is the second bid in a row where Tilcon Connecticut was low bidder. The City is extremely satisfied and is adding approximately$1.5 million in additional work for the next season

Services

  • Milling
  • Sidewalks